Raleigh, Wake County
Raleigh: State audit finds Blue Ridge Road underpass delayed to 2027, funding up 41%
The state auditor said Friday the NCDOT project near the State Fairgrounds was due in 2023. The current estimate is spring 2027. Funding rose from $50.7 million to $71.6 million.
By Triangle Local Newsroom · Published
.jpg?width=1280)
File photo: James Willamor (CC BY-SA 3.0), via Wikimedia Commons.
What we know
Confirmed
- The North Carolina Office of the State Auditor released Rapid Response Special Report RR-2026-BRUP on Friday, Oct. 16, 2026, on delays and cost increases on NCDOT's Blue Ridge Road Underpass Project in Raleigh.Confirmed by N.C. Office of the State Auditor press release and report, Oct. 16, 2026
- The project is meant to ease traffic around the N.C. State Fairgrounds by lowering Blue Ridge Road so vehicles and pedestrians can travel under Hillsborough Street, Beryl Road and the railroad.Confirmed by Auditor press release; auditor report; NCDOT I-440 and Blue Ridge Road project page
- The 2026 N.C. State Fair opened Thursday, Oct. 15, and runs through Sunday, Oct. 25.Confirmed by N.C. Department of Agriculture and Consumer Services, State Fair hours of operation
- The contract required completion no later than Aug. 1, 2023. Lane Construction Corporation proposed July 31, 2023, and that date became the contract's final completion date, the report says. The auditor's October 2025 NCDOT Division 5 timeline lists the current estimate as spring 2027.Confirmed by Auditor report, RR-2026-BRUP
- The auditor's funding table shows Blue Ridge Road project funding rose from $50.7 million on Aug. 20, 2018, to $71.6 million in 2025, a 41 percent increase. The largest single increase was a $17 million federal funding request approved by the Federal Highway Administration on March 12, 2025.Confirmed by Auditor report, RR-2026-BRUP, Table 2
- NCDOT awarded combined design-build contract C204157, covering I-440 widening (U-2719) and the underpass (U-4437), to Lane Construction Corporation on Oct. 23, 2018. NCDOT's project page lists the combined contract price as $346.2 million. The $50.7 million to $71.6 million figures are the underpass project's own funding, not the full I-440 contract.Confirmed by Auditor report; NCDOT I-440 and Blue Ridge Road project page
- The auditor said railroad right-of-entry issues delayed the project from the start, and that construction on railroad property could not begin until the right of entry was fully executed. Blue Ridge Road did not close to traffic until October 2022.Confirmed by Auditor press release and report
- NCDOT's project page says Blue Ridge Road has been closed on either side of the railroad tracks just south of Hillsborough Street since October 2022 and will remain closed until closer to the project completion date. The page lists the anticipated Blue Ridge Road completion year as 2027.Confirmed by NCDOT I-440 and Blue Ridge Road project page
- The auditor said poor soil conditions, found after construction began, added more delay. Because of railroad limits, the contractor could do only limited soil testing before work started.Confirmed by Auditor press release and report
- The contract lets NCDOT charge Lane $20,000 a calendar day in liquidated damages for missing substantial completion, and $5,000 a calendar day from then until final completion, plus other daily fees on intermediate deadlines. The auditor said NCDOT has not publicly reported whether it has charged those fees.Confirmed by Auditor report, RR-2026-BRUP
- The auditor recommended clearer Blue Ridge Road-specific public reporting, a firm standalone completion date, and public accounting of whether liquidated damages apply when milestones are missed.Confirmed by Auditor report, RR-2026-BRUP
- NCDOT's written response, dated Sept. 22, 2026, and signed by Senior Deputy Chief Engineer E. Boyd Tharrington, is included in the report. The department said it reviewed the five findings and will improve public information on the Blue Ridge Road work, including a more specific anticipated completion milestone on the project website.Confirmed by Auditor report, NCDOT response
- State Auditor Dave Boliek said in the Friday release, "North Carolinians traveling in for the State Fair have patiently waited for years on the Blue Ridge Road Underpass Project. This is a complex project and railroad issues have delayed it from the start, but the need for this underpass hasn't gone away. As this report shows, delays cost taxpayers additional dollars. Enhanced transparency and public reporting will help manage expectations and hopefully drive an additional sense of urgency."Confirmed by Auditor press release, Oct. 16, 2026
Still unknown
- Whether NCDOT has assessed, waived, reduced or deferred liquidated damages against the contractor
- A firm, contractually established Blue Ridge Road completion date; the auditor said NCDOT has not published one
- The result of NCDOT's talks with Lane on a completion date for the underpass that is separate from the I-440 widening
What this means for you
- Roads
- Blue Ridge Road has been closed since October 2022 on either side of the railroad just south of Hillsborough Street, NCDOT says, and will stay closed until closer to completion.
Instructions from N.C. Office of the State Auditor; NCDOT; N.C. Department of Agriculture and Consumer Services
This site is not NCDOT and not the State Fair. For the project, use NCDOT's I-440 and Blue Ridge Road page. For the audit, use the state auditor's report. This site is not an emergency service. If anyone is in danger, call 911.
What happened
The North Carolina Office of the State Auditor released a Rapid Response Special Report on Friday on delays and rising costs on NCDOT's Blue Ridge Road Underpass Project in Raleigh.
The work is meant to ease traffic around the N.C. State Fairgrounds by lowering Blue Ridge Road so vehicles and pedestrians can go under Hillsborough Street, Beryl Road and the railroad. The 2026 State Fair is open now and runs through Sunday, Oct. 25.
This site is not NCDOT. This site is not an emergency service.
What the auditor found
State Auditor Dave Boliek's office said the underpass was due in 2023 and is now estimated for spring 2027.
The contract required completion no later than Aug. 1, 2023. Lane Construction Corporation, the design-build contractor, proposed July 31, 2023, and that date became the contract's final completion date, the report says. An NCDOT Division 5 timeline from October 2025, cited in the report, lists the current estimate as spring 2027.
The auditor's funding table shows Blue Ridge Road project funding rose from $50.7 million in August 2018 to $71.6 million in 2025, a 41 percent increase. The largest single increase was a $17 million federal funding request that the Federal Highway Administration approved on March 12, 2025.
The underpass is part of a larger design-build contract, C204157, that also covers I-440 widening. NCDOT awarded that combined contract to Lane on Oct. 23, 2018. NCDOT's project page lists the combined contract price as $346.2 million. The auditor's $50.7 million to $71.6 million figures are the underpass project's own funding, not the full I-440 contract.
"North Carolinians traveling in for the State Fair have patiently waited for years on the Blue Ridge Road Underpass Project. This is a complex project and railroad issues have delayed it from the start, but the need for this underpass hasn't gone away," Boliek said in Friday's release. "As this report shows, delays cost taxpayers additional dollars. Enhanced transparency and public reporting will help manage expectations and hopefully drive an additional sense of urgency."
Why the work slipped
The auditor said railroad right-of-entry problems delayed the project from the start. Construction on railroad property could not begin until that right of entry was fully executed.
NCDOT awarded the combined contract in October 2018. Blue Ridge Road did not close to traffic until October 2022, the report says. NCDOT's project page says the road has been closed on either side of the railroad tracks just south of Hillsborough Street since October 2022 and will stay closed until closer to completion.
Poor soil, found after construction began, added more delay, the auditor said. Because of railroad limits, the contractor could do only limited soil testing before work started. Designers used conservative assumptions, then had to make costly changes when they hit poor soil.
The report also says CSX Transportation, Norfolk Southern Railway and the North Carolina Railroad Company each have to approve work in their rights-of-way. Under NCDOT's agreement with CSX, the railroad may take up to 30 days to review a submittal, and up to 30 more days to review one that comes back not approved.
NCDOT told the auditor it is negotiating with Lane to set a Blue Ridge Road completion date that is separate from the I-440 widening.
Daily fees in the contract
The contract lets NCDOT charge Lane $20,000 a calendar day in liquidated damages if the contractor misses substantial completion, and $5,000 a calendar day from then until final completion. Other daily fees apply to intermediate deadlines, including some tied to the State Fair.
The auditor said NCDOT has not publicly reported whether it has charged any of those fees. NCDOT communications through September 2025, cited in the report, did not say whether the agency had used the clauses.
What the auditor recommended
The report says NCDOT does not keep clear, public, Blue Ridge Road-specific performance controls, even though the contract splits that work from the I-440 widening for funding. It also says NCDOT uses a progress schedule rather than a critical-path schedule, and does not publish Blue Ridge Road-specific weather delays in a consistent or timely way.
The auditor recommended that NCDOT report the underpass costs and schedule separately, track the contract's Blue Ridge Road milestones, and say publicly whether liquidated damages apply when those milestones are missed. The report also calls for a firm standalone completion date, a monthly critical-path schedule, a log of soil and access problems found during construction, and a simple public dashboard.
NCDOT's public project page lists a Blue Ridge Road completion year of 2027. The auditor said the agency has not published a firm, contractually established completion date.
What NCDOT said
NCDOT's written response, dated Sept. 22, 2026, is in the report. Senior Deputy Chief Engineer E. Boyd Tharrington signed it.
The department said it reviewed all five findings. It said it will improve public information specific to the Blue Ridge Road work, including a more specific anticipated completion milestone on the project website. It said contract time and any liquidated damages will keep being evaluated under the contract, and that a final decision on those fees may not come until closeout.
NCDOT said railroad coordination is especially important on this kind of job. It said the design-build team already keeps a railroad submittal log, and that the Rail Division is giving more help tracking reviews.
The department said it does not propose adding a critical-path schedule to this contract. It said the contract never required one, the project is in the latter stages of construction, and it will not impose that requirement now. It also said it will not create a separate soil-and-access log at this stage, and it will not publish a running tally of weather days, because individual weather days do not automatically change the completion date.
NCDOT said it remains focused on finishing the underpass safely and will apply lessons to later projects.
Why it matters
The underpass sits next to the State Fairgrounds, and Blue Ridge Road has been closed there since 2022. The fair is open now through Oct. 25. The audit is about how long the work has taken, how much it costs, and what the public can see about progress.
Updates
Oct 18, 2026, 10:15 AM
The Office of the State Auditor posted the Rapid Response Special Report on Oct. 16. NCDOT's written response is in the report.
Sources
- Report Details Delays to Blue Ridge Road Project Aimed at Addressing State Fair Traffic (Oct. 16, 2026)
Official sourcePublished by N.C. Office of the State Auditor · Checked Oct 18, 2026, 10:20 AM
- RR-2026-BRUP, Blue Ridge Road Underpass Project, Rapid Response Special Report (first published Oct. 16, 2026)
Official sourcePublished by N.C. Office of the State Auditor · Checked Oct 18, 2026, 10:20 AM
- RR-2026-BRUP report PDF (findings, funding and completion tables, NCDOT written response dated Sept. 22, 2026)
Official sourcePublished by N.C. Office of the State Auditor · Checked Oct 18, 2026, 10:20 AM
- I-440 and Blue Ridge Road Improvements (road closed since October 2022; Blue Ridge Road completion year 2027; Lane Construction Corporation; combined contract $346.2 million)
Official sourcePublished by N.C. Department of Transportation · Checked Oct 18, 2026, 10:20 AM
- N.C. State Fair hours of operation (Oct. 15-25, 2026)
Official sourcePublished by N.C. Department of Agriculture and Consumer Services · Checked Oct 18, 2026, 10:20 AM
Related stories
File photo
Raleigh: Wake County awards a construction contract to replace EMS Station 5
The Hargrove Road station, also called Mini City, is to be rebuilt with three vehicle bays. The county says work is expected to start in January 2027.
47 minutes ago
File photo
Wake County: Commissioners approve a next step toward a school-land housing swap
The memorandum of understanding with the school system is not a final transfer. Staff still have to appraise the parcels. Both boards would have to vote again, likely before the end of fiscal year 2027.
2 hours ago
File photo
Durham: Lake Michie Park and Marina stay closed as county remains in severe drought
City reservoirs were 37% full as of Sunday. Stage 2 water rules have been in effect since June 15. Parks staff shut the marina on June 5 until the lake is high enough to use safely.
4 hours ago
.jpg?width=960)